Ready Mix Calculator

Truck count and short-load check for ready-mix concrete delivery.

Quick answer: Ready-mix trucks carry 8–10 cu yd. Divide total yards by truck capacity and round up; orders under about 4 yards usually trigger a short-load fee of $75–$150.

How to use this calculator

  1. Enter Cubic yards needed.
  2. Enter Truck capacity in cu yd.
  3. Press Calculate. The highlighted row is your order quantity; the note beneath it translates the number into real-world terms.

Formula & constants

Ready-mix trucks carry 8–10 cu yd. Divide total yards by truck capacity and round up; orders under about 4 yards usually trigger a short-load fee of $75–$150. Every default in the fields above is editable — when your supplier’s spec sheet lists a different density, coverage rate or price, enter that number instead. The waste and compaction allowances follow common trade practice; see our methodology page for the derivation of each formula and the standards it references.

Worked example. With cubic yards needed = 10, truck capacity = 10 cu yd, the calculator returns:
Trucks needed1 trucks
Short-load riskNo

Where this fits in the project

Concrete work starts below grade: excavation, then a compacted gravel base for drainage, formwork, rebar where the slab spec requires it, then the pour. Order by cubic yard and round up — a short load fee costs more than surplus material.

How this connects to your project

No quantity stands alone — each material in the chain depends on the ones around it. These are the planning steps that pair with the ready mix calculator:

Frequently asked questions

How much concrete fits in one truck?

8–10 cu yd fully loaded; local bridge limits sometimes cap it at 8.

How fast must a truck be emptied?

Most plants allow 4–7 minutes per yard; overtime standby billing follows. Have crew and access ready.

Last verified: — prices reflect current national averages. See our methodology.

Estimates are for planning. Material densities, coverage rates and prices vary by region and supplier — confirm final quantities before ordering, and check local code where structural or electrical work is involved.