Compaction Calculator

Compacted volume from loose material and target density percentage.

Quick answer: Compacted volume = loose volume × (compaction ratio). Placing at 95% Standard Proctor, 100 loose cy of granular fill finishes at roughly 85–90 cy in place, laid in 6–8 in lifts.

How to use this calculator

  1. Enter Loose volume in cu yd.
  2. Enter Compaction ratio in %.
  3. Press Calculate. The highlighted row is your order quantity; the note beneath it translates the number into real-world terms.

Formula & constants

Compacted volume = loose volume × (compaction ratio). Placing at 95% Standard Proctor, 100 loose cy of granular fill finishes at roughly 85–90 cy in place, laid in 6–8 in lifts. Every default in the fields above is editable — when your supplier’s spec sheet lists a different density, coverage rate or price, enter that number instead. The waste and compaction allowances follow common trade practice; see our methodology page for the derivation of each formula and the standards it references.

Worked example. With loose volume = 10 cu yd, compaction ratio = 88 %, the calculator returns:
Compacted volume8.8 cu yd
Volume lost1.2 cu yd

Where this fits in the project

Earthwork precedes everything: dig volumes set the budget for hauling and determine imported fill or base gravel. Bank volume expands when dug (swell) and imported fill shrinks when compacted — use the truckload calculator on loose volume, not bank volume.

How this connects to your project

No quantity stands alone — each material in the chain depends on the ones around it. These are the planning steps that pair with the compaction calculator:

Frequently asked questions

What does 95% Proctor mean?

Field density must reach 95% of the soil’s lab-established maximum dry density — the standard spec under pavements and slabs.

How thick can compaction lifts be?

6–8 in loose per lift for plate and roller compactors; thicker lifts leave uncompacted cores that settle later.

Last verified: — prices reflect current national averages. See our methodology.

Estimates are for planning. Material densities, coverage rates and prices vary by region and supplier — confirm final quantities before ordering, and check local code where structural or electrical work is involved.