By Steve Axton, PE — Licensed Civil Engineer · Updated November 2026
I start a paver order with two drawings: the edge of the finished pavement and the rows inside it. The first drawing gives me square footage. The second tells me whether the last row will take whole pavers, usable halves, or short pieces that consume a full unit each. Two patios with the same footprint can take different orders because their patterns, borders and cuts differ.
Quick answer. For a 12 × 16 ft patio with no separate border, start with 192 sq ft. If the layout calls for 10% extra, that becomes 211.2 sq ft, or six layers if the supplier only sells complete 40 sq ft layers. Add the border on its own line if it uses a different paver.

Measure the paved area inside the outline
Use the outside dimensions of the finished pavers. For a rectangle, multiply length by width. For an L shape, draw two rectangles that share an edge and add their areas once. Measure an inside corner from both directions if you can. A discrepancy at the corner changes the last cuts on both legs, even when the total area difference looks small.
Sketch anything that will remain exposed within the paving: a square planter, a drain opening, or a separate step. Subtract the area of a permanent planter. Keep the cut allowance for the pavers along its perimeter. A four-square-foot opening removes four square feet from the field, but the surrounding cut units can still use a substantial portion of the material saved.
Mark the dimensions of usable space separately from the paving outline. The patio seating layouts show why a conversation area needs clearance behind chairs. Measure that space before choosing the overall shape or committing to a border.
Use the supplier’s installed coverage
The product label may give the actual molded dimensions, a nominal module, pieces per square foot, or square feet per layer. Use the supplier’s installed coverage for the exact product and declared joint arrangement if available. A nominal module may already include the joint, so adding the same width again overstates each unit’s coverage. For a multi-size bundle, use the installed coverage of the bundle and confirm which patterns its mix supports.
Check that the pattern in the quote is the one on the plan. A running bond with the units parallel to the long edge often gives a different cut list than a diagonal pattern. Review the brick and stone pattern examples for orientation, then trace the actual rows at corners and obstacles. If you are drawn to the diagonal, compare how the herringbone layout meets its border before choosing the starting line.
| Check | What to record | Order impact |
|---|---|---|
| Straight perimeter | Length and starting grid | Counts full courses and repeatable end cuts |
| Curve or angle | Length plus locations of cut units | Can leave only one usable piece per paver |
| Separate border | Border width, linear run and corner detail | Requires its own product quantity |
| Multi-size field | Bundle coverage and pattern mix | Order by complete bundle where needed |
| Gaps filled with gravel | Actual paver grid and gap width | Changes unit count independently of footprint |
A stepped grid with open gravel gaps is a different takeoff. The paver-and-rock layout can help you set a consistent module. Divide each dimension by that module, mark actual placements on the plan, and count whole squares or stepping units. Price gravel infill separately from aggregate below the pavers.
Check the border and cut list before rounding
For a band of uniform width, subtract the area of the inner rectangle from the footprint. For a single-file edge, also count the linear runs using the repeating unit length and your planned joint. Check corners by drawing them. Mitered corners, alternating ends and special corner units may use material differently even when they cover the same area.
Decide where to start the grid by drawing the first and last courses. A small shift to the starting line can spread cuts across opposite edges and avoid a very narrow strip at a visible threshold. When you compare two starting grids, count how many whole units will go to the saw for each. A clean second piece can go elsewhere if its dimensions and intended exposed edge work for that spot.
Measure edging by the actual runs that receive it. Working along a stable curb may call for a different detail from a free edge next to lawn. Use the linear takeoff for patio edging to separate restraint lengths from border units.
Worked example: Price a 12 × 16 ft patio
- Draw the field. Multiply 12 ft by 16 ft to get 192 sq ft. This example uses one style over the entire patio, with no separate border.
- Apply the project allowance. With an illustrative 10% allowance for cuts and spares, multiply 192 by 1.10 to get 211.2 sq ft. Confirm the allowance against your own layout.
- Round to the selling increment. At 40 sq ft per layer, 211.2 ÷ 40 = 5.28 layers. Six complete layers cover 240 sq ft. Ask if the supplier sells five layers plus enough individual units to cover 11.2 sq ft.
- Record the other layers. If the selected assembly specifies 4 in. of compacted base, 192 × 4 ÷ 12 = 64 cu ft, or 2.37 cu yd, over the paved footprint. An extension beyond the edge restraint increases that volume. Ask the supplier how it converts compacted volume to delivered quantity.
An allowance is part of the layout, and pack rounding is part of the purchase. In the example, rounding adds 28.8 sq ft to the 211.2 sq ft target. Count it before paying for another layer of spare material. If the design calls for a different field and border, calculate the two allowances and round each line separately. Extra field pavers cannot resolve a shortage of matching border units.
Give the supplier enough information to quote the job
Ask for the product and color, ordering increment, and installed coverage for each line. Record the batch or lot information so you can match a later repair as closely as possible. Check the delivery arrangement separately, especially where a truck cannot get close to the staging area. An accurate takeoff does not tell you how many times each layer will be moved on site.
Keep the paver count apart from the base and bedding. CMHA’s interlocking pavement guidance treats these as separate layers, with edge restraint and surface grade addressed in the design. Base depth depends on the site and intended loading. If the pavers meet a driveway apron, use the complete asphalt paving guide to account for the adjoining pavement separately from your patio takeoff.
Next, check the patio base for low spots before placing sand.
Check the paver quantity against your layout, then use the aggregate base tool to estimate the base and the sand volume calculator to price the bedding separately.
Frequently asked questions
Can I use one waste allowance for the field and the border?
Only if the same allowance reflects both cut lists. A curved border can consume more pieces per linear foot while a straight rectangular field has repeatable cuts, so record the materials separately.
Should I subtract a small drain from the order?
Subtract its opening from the net paved area if you are using an area takeoff, then count the whole units needed to cut around it. The cut list often matters more than the area of a small opening.
How much does a half-foot border change the field area?
On a 12 × 16 ft rectangle, a uniform 6 in. border leaves an 11 × 15 ft field. The field is 165 sq ft, and the border covers 192 − 165 = 27 sq ft before cuts.
Is compacted base volume the same as loose delivery volume?
The compacted volume describes the finished layer. Ask the quarry or yard how it quotes delivery for that aggregate, because density and the relationship between loose and compacted quantities depend on the product.
Verified November 2026. Sources include CMHA PAV-TEC-002-22, Construction of Interlocking Concrete Pavements and CMHA PAV-TEC-009, Guide Specification for the Construction of Interlocking Concrete Pavement.